Hubei Wangke Template Co., Ltd. introduces that the table mold operation consists of horizontal movement, height adjustment, mold support and mold removal It consists of four processes. The first two processes are related to the scaffolding of the mold, the last process is related to the quality and design of the formwork.
(1) When assembling, check whether the parts are qualified against the drawing design and whether the installation position is correct. Whether the fasteners are tightened.
(2) All kinds of table mold panels require strict splicing. The edge of the bamboo and wood panel and the edge of the hole should be painted with the edge banding agent of the template.
(3) Before assembling the column table model, check the portal frame, frame and steel pipe one by one. Complete and defect-free, whether the fasteners and fasteners used are working normally, and do a load test if necessary.
(4) The wood used should be free from splitting, decay, etc.
(5) When using multi-layer board materials on the panel, check for damage in time and turn it over if necessary use.
(6) The gaps between the table templates, the templates and the columns and walls must be closed tightly. And pay attention to prevent the caulking from being embedded in the concrete, causing the formwork to be jammed during demolding.
(7) Before tying steel bars, all kinds of panels should be painted with effective release agent.
(8) Before pouring concrete, the formwork must be inspected and received, and the quality can be used only after the quality meets the requirements.
(9) The elastic line on the table mold should be used in two separate layers to avoid two layers of lines Confusion.
The table form is used for the construction of the cast-in-situ reinforced concrete structure standard floor. The floor template is assembled at one time. Repeated use reduces the process of assembling and dismantling the formwork layer by layer, simplifies the formwork disassembly process, saves the manpower for the formwork disassembly and disassembly, and accelerates the construction progress. Since the formwork can be hoisted by hoisting machinery as a whole, it can be used layer by layer without landing, thereby reducing the temporary stacking of formwork sites, especially in the downtown area where the construction land is tight. It has advantages in construction.